Scheduling & Capacity

Dieser Inhalt ist noch nicht in deiner Sprache verfügbar.

Eryxon Flow includes a simple capacity-based scheduler for planning operations across your production cells. It allocates work based on cell capacity and your factory calendar—not a full APS optimizer, but enough to get a clear capacity overview and planned dates on every operation.

  1. Click Auto Schedule on the Capacity Matrix page
  2. The scheduler fetches all incomplete jobs and their operations
  3. Jobs are sorted by due date (respecting any manual overrides)
  4. Operations are allocated to their assigned cells day by day, respecting daily capacity limits
  5. planned_start and planned_end dates are saved on each operation

If operations already have planned dates, a confirmation modal warns you before overwriting.

Each cell (work center) has a capacity_hours_per_day setting, configured in Admin → Stages & Cells. The scheduler never exceeds this daily limit—large operations overflow to subsequent working days.

Navigate to Admin → Factory Calendar to configure:

  • Holidays — No work scheduled (capacity = 0)
  • Closures — Factory closed (capacity = 0)
  • Half days — Reduced capacity (multiplier = 0.5)
  • Working days — Full capacity

Calendar entries override the default Monday–Friday working week.

Admins can override a job’s due date without changing the original ERP-provided date. The scheduler uses the override when prioritizing which jobs to schedule first. Override a due date from the Jobs list by clicking the calendar icon.

The Capacity Matrix page at Admin → Capacity Matrix shows:

  • Cell utilization by date in a color-coded grid
  • Green ≤50% · Yellow ≤80% · Orange ≤100% · Red overloaded
  • Click any cell/date to see which operations are allocated
  • Operations are scheduled in job due date order, not optimized for throughput
  • No cross-job dependency tracking
  • Only cell capacity is considered, not worker availability or materials
  • No what-if scenario simulation

For complex scheduling needs, use a dedicated APS tool and sync dates via the REST API, CSV Import, or one of the planning adapters below.

Eryxon Flow ships with a planning adapter interface in src/lib/planning/ that bridges external planning and scheduling tools using ISA-95 aligned vocabulary. Use it to pull work orders and resources from your planner into Eryxon and push start and completion feedback back.

AdapterStatusAuthCapabilities
FrePPLeBetaBasic AuthPull work orders + resources, push order start and completion, pagination handling
Odoo MRPBetaJSON-RPCPull work orders from mrp.production, push execution feedback

Both adapters are Beta — interfaces and behavior may still change. The FrePPLe adapter is covered by 21 unit tests (connection, mapping, pagination, error handling, auth); the Odoo adapter has narrower coverage (2 tests today). Pilot them on non-critical work first.

Select an adapter at runtime with the createPlanningAdapter(config) factory. Adapters are not enabled by default — they are an opt-in integration surface for self-hosted deployments and forks.